Cabinet received a report which provided Members with an update on the work for the HS2 project and the resources for the work. The report updated Members on the Service Level Agreement and the Funding Agreement to cover the resources being expanded on the project. The additional projects referred to in the recommendations include Colne Valley Regional Park, Chiltern Tunnel South Portal, viaduct design and additional mitigation projects including Broadwater Lake Area, Tilehouse Lane Woods Area, Harefield Moor area and Western Valley Slopes.

 

RESOLVED that

1)   the report and progress made on the project be noted;

2)   delegated authority be granted to the Chief Executive in consultation with the Leader and the Head of Legal and Democratic Services to enter into a Funding Agreement with HS2 for the delivery of the Additional Projects approved by the Colne Valley Regional Park Panel (CVRPP) under Section 1 of the Localism Act 2011; and

3)   delegated authority be granted to the Chief Executive in consultation with the Leader and the Head of Legal and Democratic Services to enter into agreements with relevant stakeholders/project leads appointed by the Colne Valley Regional Park Panel (CVRPP) for the delivery of the Additional Projects under Section 1 of the Localism Act 2011.

 

 

Publication date: 17/04/2018

Date of decision: 17/04/2018

Decided at meeting: 17/04/2018 - Cabinet

Effective from: 27/04/2018

  • Restricted enclosure  View reasons restricted